Construction of a bioclimatic gymnasium on the Tampon campus

This project falls under ERDF Action Sheet FA4.2.3 – Construction for Higher Education. Key dates: The bioclimatic gymnasium project aligns with higher education and research strategies, particularly those supporting a site-specific policy, and is also consistent with the institution's real estate strategy through […]

This project falls under the FEDER action sheet FA4.2.3 – Construction in support of Higher Education. 

Key dates:

  • May 15, 2025: validation of the expert report by the Ministry;
  • May 22, 2025: Validation of the project by the Board of Directors;
  • July 17, 2025: notification of the MOE contract to CO-ARCHITECTES Sarl following a project management competition; 
  • August 22, 2025: delivery of the APS phase;
  • the 1er October 2025: start of the APD for a period of 8 weeks;
  • The APD will be delivered on November 26, 2025.
  • On December 23, 2025, the notification of the draft ERDF agreement was sent. 

The bioclimatic gymnasium project is aligned with higher education and research strategies aimed in particular at supporting a site policy and is also consistent with the establishment's real estate strategy through its multi-year real estate strategy plan (SPSI 2018-2022) validated on July 6, 2020 by the central administration. 

This project involves the construction of a new generation sports complex on the Tampon university campus. It has been designed to be modular, with several complementary "functional building blocks" that work together to achieve the following objectives:

  • To meet the educational needs of students on the site for the STAPS program, to develop new diplomas for the professions of Sports Training and Sports Management;
  • To enable research activity in the science and technology of physical and sporting activities with the ambition of developing a "sports hub";
  • To enable SUAPS to develop a sports activity open to all students and to organize sports competitions;
  • To offer exemplary quality construction in environmental terms, particularly in terms of energy: positive energy building, energy production and storage, use of bio-sourced materials, natural cross ventilation;
  • Enabling partnerships with outside entities, particularly the municipality of Tampon, but more broadly the CIVIS and CASUD urban communities.

From a functional point of view, this gymnasium, designed as an educational and research tool for sports programs, will be structured around four hubs:

  • Multipurpose sports area;
  • Welcoming and convivial spaces;
  • Training and teaching spaces;
  • Multi-sport area with panoramic views.

Furthermore, compared to the NZEB area, the project's energy consumption ratio is
23,6 kWhEP/m²/year. This ratio complies with the NZEB requirement of 24 kWhEP/m².year.

Regarding the financial aspect of the operation, the estimated cost is €15,000,000 including VAT (i.e., €13,824,885 excluding VAT).

Its projected financing is as follows:

Total cost including VAT (in €)Total cost excluding VAT (in €)Total cost eligible for ERDF funding (excluding VAT) (in €)SPRING80% of the cost is eligible for ERDF funding.CPNBOP State 123State Additional Funding HPO – BOP 123Other audiences
15 000 00013 824 88513 435 28510 748 2282 687 0571 312 943251772
Logo of the Réunion Region

This project is funded by the European Union under the ERDF-ESF+ Réunion program, managed by the Réunion Region. Europe is investing in Réunion through the ERDF fund.